    Still no sign of my batch 625 results! Sent an open request to find out where they were and was told that there may be as many as 1000 samples in one batch and they might process only 100 per day! That's 10 days per batch. Surely not?
    Just read on another thread that somebody still waiting for batch 624 results. Confused?

    Leave a comment:


  • T0pcat
    replied
    Congratulations! Now the fun can begin. Hopefully mine won't be too far behind.
    I know that mtDNA, Autosomal, etc. take different times to process, but if you have your y-dna results from that batch, shouldn't all the others be ready at the same time? Or am I missing something?

    Leave a comment:


  • DNAJUNKIE
    replied
    Mtdna also came in this evening, Halleluiah.

    Leave a comment:


  • mitchucn
    replied
    Originally posted by DNAJUNKIE View Post
    Well, yesterday the test gets pushed back, today I get results, go figure.

    Within twenty minutes I have been contacted by a 67/67 match at zero and he confirms two other 37/37 matches at zero in my list.

    If the Mtdna full sequence is as good we may have a winner. Till then I will just wait. I will not trust the projected completion dates.
    My Y-DNA got pushed back the other day, again. But wasn't lucky enough to get my results the next day. I'm pretty annoyed and frustrated at this point with the company. I've had relatives use them and never had an issue or delay but this has been ridiculous. I'm glad people are getting their results though. At least someone has had some success.

    Leave a comment:


  • DNAJUNKIE
    replied
    Well, yesterday the test gets pushed back, today I get results, go figure.

    Within twenty minutes I have been contacted by a 67/67 match at zero and he confirms two other 37/37 matches at zero in my list.

    If the Mtdna full sequence is as good we may have a winner. Till then I will just wait. I will not trust the projected completion dates.

    Leave a comment:


  • ekc123
    replied
    SNP tests?

    Originally posted by mitchucn View Post
    Has anyone gotten their results from this batch? Of course, everything seems to be delayed except FF. Mine aren't up yet but the timeframe they posted isn't over. Just wondering if anyone is getting anything yet.
    Most of the delays seem to be related to the Y-STR tests. What about individual SNP tests? Has anyone received results for individual SNP tests on time in this batch? Last time I ordered an individual SNP test, I got the results in a couple of weeks, but recently a project to which I belong ordered an SNP test for my kit and I'm wondering what the average wait times are for these tests this summer. My expected results are due on or before the end of August according to what is posted on my page.

    Leave a comment:


  • T0pcat
    replied
    I was really excited to begin with, but now I'm just getting annoyed. I was looking forward to doing some deeper research into my DNA, but if this is what I have to look forward to I might just stop here!

    Leave a comment:


  • T0pcat
    replied
    Me too! Is this the only business where you get away with continually disappointing your customers?

    Leave a comment:


  • DNAJUNKIE
    replied
    Date pushed back again


    Y-DNA67
    Ordered 05/19/2015 625
    Batched 06/03/2015 625
    Completed Pending 625


    Y-DNA67 Y-DNA1-12 Markers 625 08/19/2015 - 09/02/2015
    Y-DNA67 Y-DNA13-25 Markers 625 08/19/2015 - 09/02/2015
    Y-DNA67 Y-DNA26-37 Markers 625 08/19/2015 - 09/02/2015
    Y-DNA67 Y-DNA38-47 Markers 625 08/19/2015 - 09/02/2015
    Y-DNA67 Y-DNA48-60 Markers 625 08/19/2015 - 09/02/2015
    Y-DNA67 Y-DNA61-67 Markers 625 08/19/2015 - 09/02/2015

    Leave a comment:


  • DNAJUNKIE
    replied
    Now Full Sequence is delayed.

    mtFull Sequence HVR1 625 08/12/2015 - 08/26/2015 Results for your mtDNA testing have been delayed. We have updated your predicted completion date, and action by you is not usually required. Note that predicted dates are an estimate and subject to lab volume and quality control.
    mtFull Sequence HVR2 625 08/12/2015 - 08/26/2015 Results for your mtDNA testing have been delayed. We have updated your predicted completion date, and action by you is not usually required. Note that predicted dates are an estimate and subject to lab volume and quality control.
    mtFull Sequence mtDNA Coding Region 625 08/12/2015 - 08/26/2015

    Leave a comment:


  • 263026
    replied
    370522

    YDNA12

    Batched 06/03/2015 625
    Completed Pending 625

    new "Expected Date" 08/05/2015 - 08/19/2015

    Leave a comment:


  • DNAJUNKIE
    replied
    As of 5:47 pm 7/15/2015

    Y-DNA67
    Ordered 05/19/2015 625
    Batched 06/03/2015 625
    Completed Pending 625

    Leave a comment:


  • Auslander
    replied
    Received my batch 625 Big Y results today!! That's 2 weeks earlier than the expected date. And that was the original date, it was never extended. Looks like the timeliness of receiving test results depends upon the test and whether there were any quality problems with the results. Wishing the rest of you 625 testers speedy results.

    Leave a comment:


  • T0pcat
    replied
    That does give me a little hope that they may be completed on time. I wont hold my breath too much though!

    Leave a comment:


  • Renegade6008
    replied
    I just want to infuse a little hope for those being delayed. I had two kits batched May 7, orig expected date of completion 6-17 through 7-1. They were delayed with a new expected completion 7-22 through 8-5. Both kits were completed on 7-7. These kits were for Y67 markers.